This year's Jiangsu 55 million tons of clinker production ca

Notice of the Jiangsu Building Materials Industry Association on the issuance of the "2019 Jiangsu Cement Industry Wrong Peak Production Shutdown and Verification Plan" (hereinafter referred to as the "Notice"), 23 enterprises involved in clinker production in Jiangsu Province, 39 production lines 2019 In the year, the peak production work was carried out. The total number of days of kiln shutdown was 65 days. The time of stopping the kiln, the number of days, and the time (including the kiln stop for 30 days from January 1 to March 31 during the Spring Festival) and the verification form were in principle referenced to Jiangsu in 2018. Province's cement industry peak production and shutdown kiln and verification program.

The notice emphasizes that enterprises that have been identified by the national or provincial industry authorities and that have achieved ultra-low emissions, or enterprises that use cement kiln to co-dispose urban domestic waste or industrial solid waste production lines, can be based on the national and local governments and environmental protection departments. The regulations and requirements for pollution control, combined with the production and operation conditions, adjust the total number of days of stopping the kiln and the time of stopping the kiln; in each kiln stop period, the county or above government, environmental protection and other industry authorities mandate the suspension or limited production. The number of days of stopping the kiln (according to the official documents and the actual execution of the kiln check record) can be included in the total number of kiln stops during the corresponding period.

2019, Jiangsu Province cement industry peak production shutdown kiln and verification program

In order to further implement the Ministry of the Environment and the Ministry of the Environment, the Yangtze River Delta Region 2018~2019 Autumn and Winter Air Pollution Comprehensive Management Action Plan (Annual Atmosphere (2018) No. 140), the provincial government issued the "Three-Year Action for Jiangsu Province to Win the Blue Sky Defence War" Plan Implementation Plan (Su Zhengfa (2018) No. 122) and the spirit of the Provincial Economic and Information Committee and the Provincial Environmental Protection Department Su Jingxin Materials "Notice on the development of peak production in the cement industry" ((2016) No. 852), now combined with 2018 The province implemented the actual situation of peak production in the cement industry, and proposed a plan to stop the kiln and check the peak production of the cement industry in our province in 2019.

First, the basic principles

On the basis of two years of experience in the work of shutting down the kiln in the cement industry in our province, combined with the actual kiln situation implemented by the local governments and environmental protection departments of the province in 2018 in response to the Blue Sky Defence Action Plan, the cement industry in our province was formulated in 2019. Peak production stop kiln and verification program.

Second, the scope of implementation

There are 23 enterprises involved in clinker production in our province, 39 production lines, and annual clinker production capacity is about 55 million tons.

Third, the number of days and time of stopping the kiln

According to the kiln requirements of local governments and environmental protection departments of our province in 2018 and the actual operation of the kiln in the peak production of cement enterprises and the typhoon production in the surrounding areas, the peak production of the cement industry in our province was stopped in 2019. The total number of days is 65 days, the kiln stop time, the number of days, the time (in which the kiln is stopped for 30 days from January 1 to March 31 during the Spring Festival) and the verification form are in principle referenced to the 2018 Jiangsu cement industry Verification plan.

Enterprises that have been identified by the national or provincial industry authorities and that have achieved ultra-low emissions, or enterprises that use cement kiln to co-dispose urban domestic waste or industrial solid waste production lines, can be based on air pollution control by the state and local governments and environmental protection departments. Regulations and requirements, combined with production and operation, adjust the total number of days of kiln shutdown and kiln shutdown time.

During each kiln stop period, the number of days of kiln stoppages (based on official documents and actual execution of kiln check records) imposed by the competent authorities of the government at the county level or above and the competent authorities of the environmental protection industry may be included in the corresponding time stop kiln. Within the total.